Customer’s Need
To create new, additional capacity for injecting biomethane into the gas grid for biomethane sourced from various biomethane plants.
Project Scope and Novel Engineering OÜ’s Role in the Project:
Main contractor for the construction of a 10-foot container for gas quality and measurement stations, which included: project design work (gas category C), container mechanics, piping, automation and electrical systems, container construction work, and technology installation, coordination with the relevant authorities (Kiwa, Gas Grid), and commissioning.
Project Duration: May – December 2024