Reconstruction of the control system for the T1 biofuel boiler and auxiliary equipment at Toftan

Customer’s Need

To modernize the control system of the existing 8 MW boiler and auxiliary equipment in order to reduce the operating personnel’s response time to boiler system alarms by creating remote management capability, thereby shortening interruptions in heat supply.

Project Scope and Novel Engineering OÜ’s Role in the Project:

Reconstruction of the existing control panel, programming work, visualization work, commissioning, training of operating personnel, and preparation of user manuals.

Project Duration: July – August 2024